Intelligent control method and system for vibroflotation construction in hydropower engineering

Qixiang FanaGuo LiaXiaochun Jiangb( )Bin MacTao ChencMeng Lic
China Huaneng Group Co., Ltd., Baoding 071799, China
Spring Energy Science and Technology Co., Ltd., Chengdu 610036, China
Sichuan Huaneng Luding Hydropower Co., Ltd., Tibetan Autonomous Prefecture of Garzê 626104, China
Show Author Information

Abstract

The vibroflotation construction is a significant measure for foundation improvement in hydropower engineering. Currently, vibro-stone columns are still constructed manually. The construction process relies mainly on the experience and responsibility of workers, which has the shortcomings of low precision in pile formation control and low degree of automation, leading to problems such as uneven pile formation, high labor intensity, and poor pile quality. This study proposes an intelligent vibroflotation control model (iVCM) based on the analysis of the pile formation mechanism and former experiences. Intelligent control of vibroflotation construction is realized through intelligent control of the vibrator current, rope pull, filler amount, and vibrator depth. A crane-type intelligent vibroflotation control system was developed to realize one-button intelligent control of pile formation. Its application in Yingliangbao Hydropower Station shows that the intelligent vibroflotation control system can regulate the construction operation of the pile formation process, improve the vibroflotation quality, reduce labor intensity, and have prospects for applicability in similar projects.

References

[1]

G. M. Wang. Application of vibration gravel pile in water conservancy projects. Technol Innovation Appl, 2014, 4: 179. (in Chinese)

[2]

W. Q. Hou. Application of vibration gravel pile in water conservancy projects. Sci Technol Inf, 2009, 7: 10. (in Chinese)

[3]

Y. Tian. Application of vibration gravel pile treatment in foundation construction of hydropower dam. Technol In-novation Appl, 2018, 8: 153–154. (in Chinese)

[4]
DL/T 5214-2016. Technical specification for vibroflotation ground treatment of hydroelectric and water resources projects. China Electric Power Press, Beijing, China, 2017. (in Chinese)
[5]

H. D. Guo. Discussion on the construction technology of composite foundation vibroflotation gravel pile. Sichuan Water Power, 2017, 36: 6–8. (in Chinese)

[6]
W. B. Lu, Z. M. Pingcuo. Application of vibroflotation method in water conservancy and hydropower projects. Sichuan Cem, 2015: 69. (in Chinese)
[7]

Z. H. Jiang, B. Lan, Z. M. Cao, et al. Application of DC-3 computer control system in the construction of vibration gravel pile. Underground Space, 2004, 24: 339–345.

[8]
J. Ye. Development and application of automatic control system in foundation treating technology with vibration–washing method. Port Sci Technol, 2012: 30–35. (in Chinese)
[9]

L. M. He. Application of automatic control system in vibration construction. China Water Transp, 2021, 21: 26–27.

[10]

Q. X. Fan, X. C. Jiang, K. X. Wang, et al. Cement grouting online monitoring and intelligent control for dam foundations. J Intell Constr, 2023, 1: 9180005.

[11]

Z. Y. Ning, P. Lin, H. Y. Peng, et al. Moving-average calculations for real-time concrete temperature monitoring. J Tsinghua Univ Sci Technol, 2021, 61: 681–687. (in Chinese)

[12]

Y. J. Wang, Y. F. Zhao, B. Liu, et al. Key technologies and future development trends of intelligent earth-rock dam construction. J Intell Constr, 2023, 1: 9180018.

[13]

D. X. Chen, P. Lin, P. Ding, et al. Vibro-stone column filling schemes based on group AHP. J Tsinghua Univ Sci Technol, 2022, 62: 1915–1921. (in Chinese)

[14]

B. Ma, D. X. Chen, M. Li, et al. Practice of construction quality management system of vibrating replacement gravel pile. Sichuan Water Power, 2023, 42: 10–13. (in Chinese)

Journal of Intelligent Construction
Article number: 9180020
Cite this article:
Fan Q, Li G, Jiang X, et al. Intelligent control method and system for vibroflotation construction in hydropower engineering. Journal of Intelligent Construction, 2024, 2(3): 9180020. https://doi.org/10.26599/JIC.2024.9180020

905

Views

221

Downloads

1

Crossref

Altmetrics

Received: 11 December 2023
Revised: 24 January 2024
Accepted: 15 February 2024
Published: 11 May 2024
© The Author(s) 2024. Published by Tsinghua University Press.

The articles published in this open access journal are distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits use, distribution and reproduction in any medium, provided the original work is properly cited.

Return